The Minto Renewal Project has been determined by the Minister for Planning to be a Major Project under the State Environmental Planning Policy (Major Projects) 2005.

This means that the Minister for Planning is the approval authority for the project under Part 3A of the Environmental Planning and Assessment Act 1979. The environmental assessment of the project has been delegated to Campbelltown City Council. 

To ensure the proper implementation of the objectives of the project, a suite of planning documents has been developed including:

  • A Concept Plan, which will guide further planning approvals for infrastructure and subdivision
  • A Development Control Plan, to provide building guidelines for Minto in line with the Concept Plan
  • A Local Environmental Plan, to rezone land in Minto in line with the Concept Plan
  • A Planning Agreement, to ensure that public areas such as parks and roads are in line with the Concept Plan

Concept Plan

23 September 2005 Department submitted its Project Application for the Concept Plan
21 October 2005 Campbelltown City Council issued Environmental Assessment Requirements for the project.
7 November 2005 The Department submitted the Environmental Assessment for the project. The submission included a draft Statement of Commitments for the project (included in the main Environmental Assessment report) and a draft Planning Agreement.
16 November 2005 -
16 December 2005
The Environmental Assessment displayed by Campbelltown City Council. A number of submission were received and subsequently addressed by the Department. However, it was considered that due to the minimal amendment required to the Concept Plan, a Preferred Project Report was not necessary.
18 April 2006 Campbelltown City Council recommended the approval of the Concept Plan to the Minister for Planning.
30 June 2006 Minister for Planning approves Concept Plan

The following are documents relating to the Concept Plan:

Development Control Plan

7 November 2005 Department submitted a proposed draft Development Control Plan with it Environmental Assessment report for the Concept Plan.
14 February -
17 March 2006
Following redrafting by Campbelltown City Council, the Council puts the Development Control Plan on display on its website and in its offices.
18 April 2006 Campbelltown City Council adopts Minto Renewal Development Control Plan.

Minto Renewal DCP

Local Environmental Plan

14 November 2005 The Department submitted a rezoning application known as the draft Local Environmental Plan (LEP).
13 December 2005 Campbelltown City Council agrees to proceed with the rezoning process.
5 July - 4 August 2006 Draft LEP put on display by Campbelltown City Council.

The following are documents relating to the Local Environmental Plan:

Draft Planning Agreement

7 November 2005 The Department submitted a proposed draft Planning Agreement with its Environmental Assessment report for the Concept Plan.
16 November 2005 - 18 April 2006 Draft Planning Agreement placed on display by Campbelltown City Council.
18 April 2006 Campbelltown City Council endorses the principles of the draft Planning Agreement. The agreement is to be expected at a later date.